Site readiness

A site-readiness record sets down measurements and supply requirements before a machine-tool delivery is booked. One written checklist gives your rigger and electrician the same facts for access, floor, electrical supply, isolator and space.

A man in safety glasses adjusts a metal lathe in a blue and grey workshop.

Access and floor checks

Machine class, landed weight, largest loose item, offload point and final position belong in the readiness record. The smallest opening must be measured at every doorway, gate or roller shutter the machine must pass through.

Concrete condition, footprint limits, anchor restrictions and load-restricted areas belong in the floor notes.

Measured internal path notes must give your rigger the route from offload point to machine position:

  • A measured gate, doorway or roller shutter width at the access opening.
  • The tightest turn between the offload point and the final machine position.
  • Each floor change, trench cover, drain, ramp or step along the internal movement.
  • Ground condition at the offload point and at the intended machine footprint.

Supply and isolator details

Required voltage, phase, full-load current and breaker rating must come from the machine information supplied. DB board capacity needs comparison with those figures before cable work is planned.

Local isolator position must let your operator and electrician reach it without crossing moving machine areas. Written labels must state the isolator rating and machine allocation for later fault checks.

Cable entry, earthing arrangement, phase rotation check and open space around the panel belong in the readiness record. Switchgear dust and footprint oil belong on the readiness list, not in verbal instructions.

Machine clearance area

Allow tailstock travel, table movement, chuck removal, swarf clearing and coolant access in the final position. Include space for pallet jack handling where tooling, material or repair work must move near the machine.

Control-side clearance must allow safe standing and panel access. All chucks, steadies, guards, coolant items and manuals must move with the machine.

Final booking depends on written figures reaching head office, including any later change to access, supply or position.